Sample Cost
Let the Numbers speak

 



 

Aqua Proof  
Links
Back

Up
Why Aquaproof
Sample Cost

 
 
 
 

Galvanised Iron Pipe & Fittings

 

Aquaproof PP-r Pipe & Fittings

Item Description Qty @ Total Item Description Size Qty @ Total
1 Pipe 1" 8 900 7200 1 PN16 - Pipe 32mm 2 912 1824
2 Pipe 3/4" 2 590 1180 2 Socket 32mm 4 53 212
3 Pipe 1/2" 2 455 910 3 Tee 32mm 5 76 380
4 Non_Return Valve 1" 2 1065 2130 4 Reducer Socket 32-25mm 3 43 129
5 Gate Valve 1" 1 630 630 5 Threaded Male Joint 32 x 1" 3 506 1518
6 Union 1" 4 56 224 6 Threaded Male Joint 25mmx3/4" 2 272 544
7 Union 3/4" 2 46 92 7 Female Threaded Tee 25mm x 3/4" 2 340 680
8 Tee 1" 7 36 252 8 Bend 90 25mm 10 45 450
9 Elbow 1" 7 24 168 9 PN16 - Pipe 25mm 25mm 2 502 1004
10 Socket 1" 8 21 168 10 Screwcock 25mm 1 898 898
11 Nipple 1" 3 26 78 11 Socket 25mm 10 37 370
12 Reducer 1 - 3/4" 2 20 40 12 Tee 25mm 6 53 318
13 Reducer 1 - 1/2" 3 20 60 13 Reducer Socket 25-20mm 3 39 117
14 PTFE Tape 4 15 60 14 Reduced Tee 25/20 25-20 mm 4 63 252
15 Hemp 6 15 90 15 Threaded Male Joint 20mmx1/2" 3 239 717
16 Putty 10 32 320 16 Bend 90 20mm 6 40 240
0 17 Crossover PN 20 20mm 1 119 119
0 18 PN16 - Pipe 20mm 20mm 5 315 1575
19 Screwcock 20mm 1 866 866
20 Socket 20mm 5 31 155
21 Tee 20mm 3 40 120
22 GI Gate Valve 1" 1 630 630
Material cost 13602 Material cost 13118
Labour (Days) 5 8500 42500 Labour (Days) 2 8500 17000

Total Cost Kshs

56102

Total Cost  KShs 

30118

 

Notes:

This sample is an existing installation that was converted to PP-r

The Header Tank and Boiler(150L) were not replaced and  retained the original GI fittings

Component costs were higher but a significant saving in labour results in lower overall cost.

PP-r installation permits the installation of booster pumps and hi-temp

PP-r installation has a life time of over 50 years (Min. EU std)

PP-r is a one time no comeback installation.

Repairs to damaged installations are both quick and simple.

For a free
 quotation 
please call:

Derek D'Costa

Tel: 721165

or 

Email:

 

 

 

Regardless of the actual labour rate per day, the enormous reduction in installation time results in a significant saving in total cost.